Wednesday, April 28, 2010

Concrete floor is almost finished!

Just a few more yards and the basement floor will be done!

Wednesday, April 14, 2010

Progress on the office

We are making slow but steady progress. On Monday we were blessed to
have two experienced builders help us for a while! Keep us in your
prayers - 12 inch blocks are heavy!

Friday, April 9, 2010

First row!

James is pictured laying the first row of block - it's coming together.
Please keep us in your prayers.

Mixing the mortar

Here is Paul mixing the mortar - a very critical job.

Sunny day!

Praise the Lord for a beautiful sunny day to start laying block. The
crew pictured below is receiving counsel from Doug, an experienced
builder.

Block arrives on rainy day

The block arrived yesterday during a strong rainstorm... it's in
God's hands!

Tuesday, April 6, 2010

New Office

Today we poured the footing for the new LIGHT office in Wildwood, GA.

We are moving forward in faith and are planning to start laying the block tomorrow!

Below is a slide show of the site:



Keep us in your prayers! If you would like to help us in any way with this project we would appreciate it.